In the next couple weeks expect to
see work on the sidewalk, bridge deck, and pavement approaches. There will be
lots of trucks in and out of the work zone. Please continue to be conscious of
the area and the direction from occasional flaggers. Thank you for your
patience.
Wednesday, April 19, 2017
Friday, April 7, 2017
Project Update: Friday, April 7, 2017
The new beams for Chestnut Avenue
bridge will be delivered and installed on Tuesday, April 11. There will be
short term full closures of Chestnut Avenue bridge beginning at 9 am for several
hours. Please seek alternate routes during this time period. Much more above
ground work to come once the beams are installed! Continue to proceed
cautiously through the work zone and thank you for your patience.
Monday, April 3, 2017
Project Update: Monday, April 4, 2017
This week and last week, the
contractor has been removing the old bridge abutment walls, and installing the
new substructure. This work is in preparation of placing the new bridge beams.
As a reminder, there are no right turns permitted from Tanglewood Drive onto Chestnut Avenue.
Thanks for your continued patience.
Please be cautious while traveling through the area as construction traffic is
entering/exiting the work zone.