Tuesday, November 22, 2016

Project Update: Tuesday, November 22, 2016

The first stage of bridge construction has been completed and open for traffic! Thank you for your patience. See you next spring!

Monday, November 14, 2016

Project Update: Monday, November 14, 2016

The project is in the final stages for the season. The south side of the bridge is scheduled to open up the week of Thanksgiving.

This past week, repaving has been completed and the winter traffic configuration has begun to be installed. The final concrete for the wall across the bridge was poured today. Throughout the next several weeks, final details including water main, fence, sidewalk and landscaping will be worked on.

Please continue to be cautious through the area and watch for an update on the traffic configuration for the winter months.