Last week there was a lot of behind the scenes action to
coordinate our upcoming work. We have
coordinated with the contractor and ComEd to begin temporary traffic signal
installation.
Advance warning signs are being posted in preparation of the
coming truck detour and lane closures across the bridge.
We are in the process of procuring the traffic signals, and
plan to begin installing the signals at the end of this week. ComEd will be
able to energize the signals a week or two after the signals are installed.
Expect to see temporary daily lane closures this week for the
traffic signal installation. However, all lanes will be reopened at the end of
the workday. The full time lane closure on the bridge deck as well as bridge
demolition work will not begin until the traffic signal is completely installed
and is operational. This closure is
expected to begin in 2-3 weeks.
Please take time to try some alternate routes this week. We
are encouraging everyone to use Chestnut Avenue only as needed during
construction to keep traffic delays to a minimum.