Monday, October 31, 2016

Project Update: Monday, October 31, 2016

Last week the contractor was able to install the new curb and gutter for the widened pavement as well as begin pouring the parapet wall that runs along the edge of the bridge. In the upcoming weeks, parapet wall, utility items, final bridge work, sidewalk and pavement surface should be completed. Once this has concluded, the construction site will close down for the winter.


Please bear with us for the final push to finish up the southern half of the bridge!

Thursday, October 13, 2016

Project Update: Thursday, October 13, 2016

Now that the beams are installed, you will begin to see the new sidewalk and wall on the south side being installed. In the coming weeks, the area will begin to look like a normal road with sidewalk, curb and gutter, and new pavement. The southern portion of the bridge is scheduled to be completed this year. Thank you for your continued patience! 

Monday, October 3, 2016

Project Update: Monday, October 3, 2016

On Tuesday, October 4, Lorig Construction will be placing new beams for the south half of the Chestnut Avenue bridge.  Starting at 9:00 am, there will be intermittent traffic stops and delays for approximately 5 minutes or less as the beams are removed from trucks and placed onto the bridge.  The work should be complete by 1:00 pm and traffic should return to normal.