In the next couple weeks expect to
see work on the sidewalk, bridge deck, and pavement approaches. There will be
lots of trucks in and out of the work zone. Please continue to be conscious of
the area and the direction from occasional flaggers. Thank you for your
patience.
Wednesday, April 19, 2017
Friday, April 7, 2017
Project Update: Friday, April 7, 2017
The new beams for Chestnut Avenue
bridge will be delivered and installed on Tuesday, April 11. There will be
short term full closures of Chestnut Avenue bridge beginning at 9 am for several
hours. Please seek alternate routes during this time period. Much more above
ground work to come once the beams are installed! Continue to proceed
cautiously through the work zone and thank you for your patience.
Monday, April 3, 2017
Project Update: Monday, April 4, 2017
This week and last week, the
contractor has been removing the old bridge abutment walls, and installing the
new substructure. This work is in preparation of placing the new bridge beams.
As a reminder, there are no right turns permitted from Tanglewood Drive onto Chestnut Avenue.
Thanks for your continued patience.
Please be cautious while traveling through the area as construction traffic is
entering/exiting the work zone.
Friday, March 24, 2017
Project Update: Friday, March 24, 2017
Crews
will be removing the beams from the north half of the Chestnut Avenue bridge,
which is undergoing demolition and replacement.
Because
placement of a large crane on the roadway is necessary, traffic that is
now reduced to one lane of travel for both directions will be intermittently
stopped and delayed from about 5 minutes while the beams are removed and placed
on trucks to be hauled away.
The
work is expected to be take place between 9 a.m. and 1 p.m. Monday, March 27.
Your patience is appreciated as this work is
necessary for completion of the project.
Wednesday, March 15, 2017
Project Update: Wednesday, March 15, 2017
Work on Chestnut Avenue bridge was
delayed by snow the past two days, however the construction site is up and
running today. The next several days will involve removing part of the old
substructure and constructing the new substructure for the north side of the
bridge. Equipment and trucks will be traveling in and out of the work zone,
please proceed with caution. Thanks for your patience.
Thursday, March 2, 2017
Project Update: Thursday, March 2, 2017
This week has included work
locating existing utilities as well as removing the existing bridge deck. Crane
assembly began today on the north side of Chestnut Avenue bridge. Expect a high increase in the noise and vibration levels beginning Friday and continuing into next week, as the while the contractor installs the temporary soil
retention system. Similar to last year,
these sheet piles will enable to contractor to expose the existing abutment
footing and install the proposed drill shafts for the new bridge. The contractor will
be monitoring the noise and vibration levels to assure that they stay within
the established standards.
Please continue to be cautious
while traveling through the work zone and we appreciate your patience!
Tuesday, February 21, 2017
Project Update: Tuesday, February 21, 2017
The construction of the north side
of Chestnut Bridge will begin Monday, February 27, 2017. From Monday until
bridge completion, the temporary traffic signal will be utilized. Once the
temporary signal is turned back on, traffic will use into the one-lane Chestnut
over the bridge, similar to last year. Please consider taking an alternative
route Monday, February 27 since delays will be expected. Proceed with caution
through the work zone as construction vehicles and workers will be present.